The most recent information regarding highway projects in the FY 2020-2029 TIP, listed alphabetically by primary road name, is provided below. All other projects are either in the Design or Right-of-way phase of development. A map of the projects may be seen at 2020 TIP Poster with spreadsheet. You may view these projects interactively by accessing the map here.
BELL FORK ROAD/COUNTRY CLUB RD INTERSECTION IMPROVEMENTS (U-6082)
This project will add turn lanes and medians at the intersection.
Status: In Design
Estimated Construction: 2028
COMMERCE Road EXTENSION
(U-5878)
This project will extend Commerce Rd from its current terminus to Country Club Dr and on to Piney Green Rd.
Status: Under Construction
Estimated Construction Completion: 2024
BELL FORK ROAD/COUNTRY CLUB RD INTERSECTION IMPROVEMENTS
(U-6082)
This project will add turn lanes.
Estimated construction: 2027
Status: Design
COMMERCE DRIVE EXTENSION
(U-5878)
This project will extend Commerce Dr from its current terminus to Country Club Dr and on to Piney Green Rd.
Estimated construction: 2021
Status: Design
NC 24 FREEDOM HIGHWAY SUPERSTREET (W-5703D)
This project will replace the crossovers on NC 24 Freedom Hwy at Baker Rd and Hunters Trail with a superstreet style
Estimated construction: 2024
Status: Design
GUM BRANCH ROAD IMPROVEMENTS (U-4906)
This project will add paved shoulders, turn lanes, minor geometry improvements and intersection improvements.
Status: Under Construction
Estimated Construction Completion: 2024
Public Meeting Maps:
GUM BRANCH ROAD IMPROVEMENTS (U-5793A/U-5793B)
This project will be completed in an A section and a B section. Section A will upgrade the portion of Gum Branch Road from Summersill School Road to Ramsey Road to a super street design. Section B will upgrade the portion of Gum Branch Road from Ramsey Road to County Club Boulevard to a super street design.
Estimated Construction: 2030
Status: In Design
GUM BRANCH ROAD IMPROVEMENTS (U-6200)
This project will upgrade the section of Gum Branch Road between Williamsburg Parkway and Indian Drive to a super street design.
Estimated Construction: 2030
Status: In Design
GUM BRANCH ROAD IMPROVEMENTS (U-5793AB)
This project will be completed in an A section and a B section. Section A of this project will upgrade the portion of Gum Branch Road from Summersill School Road to Ramsey Road to a super street design. Section B of this project will upgrade the portion of Gum Branch Road from Ramsey Road to County Club Boulevard to a super street design.
Estimated Construction: 2029
Status: Design
GUM BRANCH ROAD IMPROVEMENTS (U-6200)
This project will upgrade the section of Gum Branch Road between Williamsburg Parkway and Indian Drive to a super street design.
Estimated construction: 2030
Status: Design
HENDERSON DRIVE IMPROVEMENTS (U-5903)
This project will upgrade Henderson Drive from Gum Branch Road to Western Boulevard to a super street design.
Estimated Construction: 2030
Status: In Design
JACKSONVILLE PARKWAY EXTENSION (U-5791A)
This project will extend Jacksonville Parkway from its current terminus to Ramsey Rd, with widening to multilanes.
Estimated Construction: 2028
Status: In Design
JACKSONVILLE PARKWAY Extension (U-5791B)
This project will widen Ramsey Road from the Jacksonville Parkway Extension to US 17 (New Bern Highway).
Estimated Construction: N/A
Status: In Design
HENDERSON DRIVE IMPROVEMENTS
(U-5903)
This project will upgrade Henderson Drive from Gum Branch Road to Western Boulevard to a super street design.
Estimated Construction: 2029
Status: Design
JACKSONVILLE PARKWAY EXTENSION (U-5791A)
This project will extend Jacksonville Parkway from its current terminus to Ramsey Rd.
Estimated construction: 2024
Status: Design
JACKSONVILLE PARKWAY
(U-5791B)
This project will widen Ramsey Road from the Jacksonville Parkway Extension to US 17 (New Bern Highway).
Estimated construction: N/A
Status: Design
MARINE BLVD/GUM BRANCH RD/Bell Fork Rd INTERSECTION IMPROVEMENTS (U-5728)
This project will add turn lanes and other improvements at the intersection of Gum Branch Road and Bell Fork Road.
Estimated Construction: 2025
Status: Construction
LEJEUNE BLVD ACCESS MANAGEMENT IMPROVEMENT (U-5741)
This project will install curb, gutter and sidewalk on the north side between Bell Fork Rd and the Northeast Creek bridge and improve left turn/U-turn movements.
Estimated Construction: 2031
Status: In Design
MARINE BLVD/HENDERSON DR/ONSLOW DR INTERSECTION IMPROVEMENTS (U-5950)
This project will modify the intersections/streets to alleviate backups in the intersections.
Estimated Construction: 2027
Status: In Design
MARINE BLVD/GUM BRANCH ROAD INTERSECTION IMPROVEMENTS
(U-5728)
This project will add turn lanes.
Estimated construction: 2025
Status: Construction
LEJEUNE BLVD ACCESS MANAGEMENT IMPROVEMENT (U-5741)
This project will install curb, gutter and sidewalk on the north side between Bell Fork Rd and the Northeast Creek bridge and improve left turn/U-turn movements.
Estimated construction: 2031
Status: Design
MARINE BLVD/HENDERSON DR/ONSLOW DR INTERSECTION IMPROVEMENTS (U-5950)
This project will modify the intersections/streets to alleviate backups in the intersections.
Estimated construction: 2027
Status: Design
MARINE BLVD/US 17 PARTIAL INTERCHANGE (U-5951)
This project replace the signalized intersection with a partial interchange to allow northbound Marine Blvd traffic to continue on US 17 or access Jacksonville Parkway.
Estimated Construction: 2028
Status: In Design
U-5951 Diverging Diamond Concept U-5951 25% Design Plans
US 258 RICHLANDS HIGHWAY SUPERSTREET (U-5739)
This project will replace the center turn lane with a median and construct left turn cross-overs at key locations between Pony Farm Road and NC 53.
Estimated Construction: 2030
Status: In Design
NC 111 EXTENSION (U-5733)
This project will extend NC 111 from US 258 to the intersection of Gum Branch Road and Ramsey Road.
Estimated Construction: N/A
Status: In Design
MARINE BLVD/WESTERN BLVD INTERSECTION IMPROVEMENTS
(U-4007E)
This project will add turn lanes and through lanes from US 17 to Exchange Drive.
Estimated Construction: 2030
Status: In Design
US 258 RICHLANDS HIGHWAY SUPERSTREET (U-5739)
This project will replace the center turn lane with a median and construct left turn cross-overs at key locations between Pony Farm Rd and NC 53.
Estimated construction: 2030
Status: Design
NC 111 EXTENSION (U-5733)
This project will extend NC 111 from US 258 to the intersection of Gum Branch Rd and Ramsey Rd.
Estimated construction: Unknown
Status: Design
MARINE BLVD/WESTERN BLVD INTERSECTION IMPROVEMENTS
(U-4007E)
This project will add turn lanes and through lanes.
Estimated construction: 2029
Status: Design
NC 210 WIDENING (U-5949)
This project will widen NC 210 from US 17 Wilmington Hwy to just south of the intersection with Old Folkstone Road.
Estimated Construction: 2032
Status: In Design
US 258/NC 24/NC 53 INTERCHANGE (U-5716)
This project will convert the existing intersection to an interchange.
Estimated construction: 2030
Status: In Design
NC 210 WIDENING (U-5949)
This project will widen NC 210 from US 17 Wilmington Hwy to just south of the intersection with Old Folkstone Rd.
Estimated construction: 2030
Status: Design
US 258 RICHLANDS HIGHWAY SUPERSTREET (U-5739)
This project will replace the center turn lane with a median and construct left turn cross-overs at key locations between Pony Farm Rd and NC 53.
Estimated construction: 2030
Status: Design
NC 172 SNEADS FERRY ROAD WIDENING (W-5602)
This project will add a center turn lane and paved shoulders between Dunn Road and the bridge.
Estimated Construction Completion: Fall 2021
Status: Under Construction
TRADE STREET EXTENSION (U-5787)
This project will extend Trade Street on new location to McDaniel Drive.
Estimated construction: 2026
Status: In Design
US 258/NC 24/RHODESTOWN FIRE DEPT ROAD (U-6148)
This project will add a right turn lane on northbound US 258 and a right turn lane on Rhodestown Fire Department Road.
Estimated Construction: 2030
Status: In Design
TRADE STREET EXTENSION (U-5787)
This project will extend Trade St on new location to McDaniel Dr.
Estimated construction: 2024
Status: Design
U-5787 Concept 2 U-5787 Penny Lane Concept U-5787 Proposed Ponds U-5787 Revised Draft Feasibility Study
US 258/NC 24/NC 53 INTERCHANGE
(U-5716)
This project will convert the existing intersection to an interchange.
Estimated construction: 2029
Status: Design
US 258/NC 24/RHODESTOWN FIRE DEPARTMENT ROAD (U-6148)
This project will add a right turn lane on northbound US 258 and a right turn lane on Rhodestown Fire Department Road.
Estimated Construction: 2028
Status: Design
WESTERN BLVD ACCESS MANAGEMENT IMPROVEMENT (U-5736)
This project will convert the existing center turn lane to a median and construct left-turns at strategic locations. Also will include a multiuse path on the north side and sidewalk on the south.
Estimated construction: 2030
Status: In Design
WESTERN BLVD CULVERT REPLACEMENT (U-5508)
This project will replace the culvert under Western Blvd at Lejeune Blvd.
Estimated construction: 2030
Status: In Design
WESTERN BLVD SUPERSTREET (U-6081)
This project will add a through lane and convert most intersections to superstreet between Marine Blvd and Gum Branch Road.
Estimated construction: 2030
Status: In Design
WESTERN BLVD ACCESS MANAGEMENT IMPROVEMENT (U-5736)
This project will convert the existing center turn lane to a median and construct left-turns at strategic locations. Also will include a multiuse path on the north side and sidewalk on the south.
Estimated construction: 2029
Status: Design
WESTERN BLVD CULVERT REPLACEMENT (U-5508)
This project will replace the culvert under Western Blvd at Lejeune Blvd.
Estimated construction: 2029
Status: Design
WESTERN BLVD SUPERSTREET (U-6081)
This project will add a through lane and convert most intersections to superstreet between Marine Blvd and Gum Branch Rd.
Estimated construction: 2030
Status: Design
WESTERN BLVD/JACKSONVILLE PARKWAY INTERSECTION IMPROVEMENT (U-5789)
This project will add turn lanes.
Estimated construction: 2025
Status: Construction
WESTERN BLVD/GUM BRANCH ROAD INTERSECTION IMPROVEMENTS
(U-5319)
This project will add turn lanes.
Estimated Completion: May 2020
Status: Construction
WESTERN BLVD/JACKSONVILLE PARKWAY INTERSECTION IMPROVEMENT (U-5789)
This project will add turn lanes.
Estimated construction: 2025
Status: Construction
TRADE STREET EXTENSION (U-5787)
This project will extend Trade St on new location to McDaniel Dr.
Estimated construction: 2024
Status: Design
U-5787 Concept 2 U-5787 Penny Lane Concept U-5787 Proposed Ponds U-5787 Revised Draft Feasibility Study
US 17 WILMINGTON HIGHWAY/CURTIS ROAD/OLD MAPLEHURST ROAD INTERCHANGE (U-5735)
This project will upgrade existing intersection to a full movement interchange.
Estimated construction: 2031
Status: In Design
US 17 WILMINGTON HIGHWAY AT MCDANIEL DRIVE/WORKSHOP LANE (U-6107)
This project improve the intersection of US 17N and McDaniel Dr/Workshop Ln. It will improve pedestrian facilities at this location and will also improve drainage.
Estimated construction: 2033
Status: In Design
US 17 WILMINGTON HIGHWAY/CURTIS ROAD/OLD MAPLEHURST ROAD INTERCHANGE (U-5735)
This project will upgrade existing intersection to a full movement interchange.
Estimated construction: 2029
Status: Design
US 17 WILMINGTON HIGHWAY AT MCDANIEL DRIVE/WORKSHOP LANE (U-6107)
This project improve the intersection of US 17N and McDaniel Dr/Workshop Ln. It will improve pedestrian facilities at this location and will also improve drainage.
Estimated construction: 2027
Status: Design
US 17 WILMINGTON HIGHWAY SUPERSTREET (U-6065)
This project will include intersection improvements to include a permanent signal at U.S. 17 and N.C. 172 keeping this as a traditional signalized T-intersection. A signal would also be added at the intersection of U.S. 17 and Old Folkstone Road allowing left-turns onto Old Folkstone Road, and right-turns onto U.S. 17.
US 17 WILMINGTON HIGHWAY SUPERSTREET (U-6065)
This project will modify the crossovers at NC 172 and Old Folkstone Rd to superstreet style.
Estimated construction: 2026
Status: Design
A public meeting was held in July 2019 where two alternatives were presented. These alternatives are subject to change based on public comments received as well as updating the information based on developments in the area. Additional information can be found on NCDOT’s website and maps of both alternatives are below: