Recent information regarding roadway projects in the FY 2024-2033 STIP, is provided below, listed alphabetically by primary road name. All other projects are in the Design or Right-of-Way phase of development. You can view these projects interactively by accessing the Transportation Projects Map.

  • Bell Fork Road/Country Club Rd Intersection Improvements (U-6082)

    This project will add turn lanes, medians, and sidewalks at the intersection. Bike lanes will be installed along Country Club Rd. and Hargett St.

    Status: In Design and Right-of-Way

    Estimated Construction: June 2028

  • Commerce Road Extension (U-5878)

    This project will extend Commerce Rd from its current terminus to Country Club Dr and on to Piney Green Rd.

    Status: Completed

    Commerce at Piney Green

  • Gum Branch Road Improvements (U-4906)

    This project will add paved shoulders, turn lanes, minor geometry improvements and intersection improvements.

    Status: Completed

    Public Meeting Maps:

  • Gum Branch Road Improvements (U-5793A/U-5793B)

    This project will be completed in “A” and a “B” sections. Section A will upgrade the portion of Gum Branch Road from Summersill School Road to Ramsey Road to a super street design. Section B will upgrade the portion from Ramsey Road to County Club Boulevard to a super street design.

    Status: Unfunded, In Design

    Estimated Construction: Section A, N/A

  • Gum Branch Road Improvements (U-6200)

    This project will upgrade Gum Branch Road from Williamsburg Parkway to Indian Drive with reduced conflict intersections.

    Status: Unfunded, In Design

    Estimated Construction: N/A

  • Gum Branch Road Sidewalks Design (BL-0073)

    This project will construct pedestrian improvements along Gum Branch Road, from Onsville Drive to Onsville Drive. In its current condition, sections of sidewalk have portions on either side of the road that need new 5’ sidewalks, necessary infill for portions that are incomplete, and curb ramps. Sidewalks within the project area will be evaluated and brought up to current ADA standards.

    Status: In Design

    Estimated Construction: 2026

  • Henderson Drive Improvements (U-5903)

    This project will upgrade Henderson Drive from Gum Branch Road to Western Boulevard with reduced conflict intersections.

    Status: In Design

    Estimated Right-of-Way: 2028

    Estimated Construction: 2030

  • Jacksonville Parkway Extension (U-5791A)

    This project will extend Jacksonville Parkway from its current terminus to Ramsey Rd, with widening to multi-lanes. This also includes extension of Henderson Dr to connect to N Commons Drive.

    Status: In Design

    Estimated Right-of-Way: 2027

    Estimated Construction: 2029

  • Jacksonville Parkway Extension (U-5791B)

    This project will widen Ramsey Road from the Jacksonville Parkway Extension to US 17 (New Bern Highway).

    Status: Unfunded, In Design

    Estimated Construction: N/A

  • Marine Blvd/Bell Fork Rd Intersection Improvements (U-5728)

    This project will add turn lanes and other improvements at the intersection of US-17 BUS (Marine Blvd) and Bell Fork Road.

    Status: In Right-of-Way

    Estimated Construction: 2026

  • Lejeune Blvd Access Management Improvement (U-5741)

    This project will install curb, gutter and sidewalk on the north side between Bell Fork Rd and the Northeast Creek bridge and improve left turn/U-turn movements.

    Status: Unfunded, In Design

    Estimated Construction: N/A

  • Marine Blvd/Henderson Dr/Onslow Dr Intersection Improvements (U-5950)

    This project will modify the intersections/streets to alleviate backups in the intersections.

    Estimated Right-of-Way: 2025

    Estimated Construction: 2027

     

  • Marine Blvd/US 17 Partial Interchange (U-5951)

    This project replace the signalized intersection with a partial interchange to allow northbound Marine Blvd traffic to continue on US 17 or access Jacksonville Parkway.

    Status: In Design

    Estimated Right-of-Way: 2027

    Estimated Construction: 2029

  • US 258 Richlands Highway Superstreet (U-5739)

    This project will replace the center turn lane with a median and construct left turn cross-overs at key locations between Pony Farm Road and NC 53.

    Status: In Design

    Estimated Right-of-Way: 2028

    Estimated Construction: 2030

  • NC 111 Extension (U-5733)

    This project will extend NC 111 from US 258 to the intersection of Gum Branch Road and Ramsey Road.

    Status: Unfunded, In Design

    Estimated Construction: N/A

  • Marine Blvd/Western Blvd Intersection Improvements (U-4007E)

    This project will add turn lanes and through lanes from US 17 to Exchange Drive.

    Status: In Design

    Estimated Right-of-Way: 2028

    Estimated Construction: 2031

  • NC 210 Widening (U-5949)

    This project will widen NC 210 from US 17 Wilmington Hwy to just south of the intersection with Old Folkstone Road.

    Status: In Design

    Estimated Right-of-Way: 2030

    Estimated Construction: 2034

  • US 258/NC 24/NC 53 Interchange (U-5716)

    This project will convert the existing intersection to an interchange.

    Status: In Design

    Estimated Right-of-Way: 2028

    Estimated Construction: 2031

  • Trade Street Extension (U-5787)

    This project will extend Trade Street on new location to McDaniel Drive.

    Status: In Design

    Estimated Right-of-Way: 2026

    Estimated Construction: 2029

  • US 258/NC 24/Rhodestown Fire Dept Road (U-6148)

    This project will add a right turn lane on northbound US 258 and a right turn lane on Rhodestown Fire Department Road.

    Status: Unfunded, In Design

    Estimated Construction: N/A

  • Western Blvd Access Management Improvement (U-5736)

    This project will convert the existing center turn lane to a median and construct left-turns at strategic locations. Also will include a multiuse path on the north side and sidewalk on the south.

    Status: In Design

    Estimated Right-of-Way: 2028

    Estimated Construction: 2030

  • Western Blvd Culvert Replacement (U-5508)

    This project will replace the culvert under Western Blvd at Lejeune Blvd.

    Status: In Design

    Estimated Right-of-Way: 2028

    Estimated Construction: 2030

  • Western Blvd Superstreet (U-6081)

    This project will add a through lane and convert most intersections to reduced conflict intersections between Marine Blvd and Gum Branch Road.

    Status: Unfunded, In Design

    Estimated Construction: N/A

  • Western Blvd/Jacksonville Parkway Intersection Improvement (U-5789)

    This project will add turn lanes.

    Status: Construction

  • US 17 Wilmington Highway/Curtis Road/Old Maplehurst Road Interchange (U-5735)

    This project will upgrade existing intersection to a full movement interchange.

    Status: In Design

    Estimated Right-of-Way: 2028

    Estimated Construction: 2032

  • US 17 Wilmington Highway at McDaniel Drive/Workshop Lane (U-6107)

    This project improve the intersection of US 17N and McDaniel Dr/Workshop Ln. It will improve pedestrian facilities at this location and will also improve drainage.

    Status: Unfunded, In Design

    Estimated Construction: N/A

  • US 17 Wilmington Highway Superstreet (U-6065)

    This project will include intersection improvements to include a permanent signal at U.S. 17 and N.C. 172 keeping this as a traditional signalized T-intersection. A signal would also be added at the intersection of U.S. 17 and Old Folkstone Road allowing left-turns onto Old Folkstone Road, and right-turns onto U.S. 17.

    Status: Right-of-Way 2025

    Estimated Construction: 2028

  • Northeast Creek Bridge Replacement (BR-0193)

    This project will replace bridge No. 7 over Northeast Creek on N.C. 24 (Lejeune Blvd.).

    Status: In Right-of-Way

    Estimated Construction: 2028

  • Queen Creek Bridge Replacement (B-5944)

    This project will replace bridge No. 77 over Queen Creek along Queens Creek Road, with a new structure that will accommodate future traffic and roadway needs.

    Status: In Design

    Estimated Right-of-Way: 2031

    Estimated Construction: 2033